Middle Deepdale unadopted roads
Why many roads on Middle Deepdale in Eastfield are still not adopted, what the Section 38 agreements say, who looks after lights and grit bins until adoption, and what the council has told me.
What adoption means
Road adoption is when the council takes over responsibility for a road that was private. On a new estate the developer builds the roads to the council's standard under a Section 38 agreement, made under the Highways Act 1980 [1][2]. Each Middle Deepdale agreement also has a bond, so the council has money to finish the roads if the developer does not (FOI CN48965). Until a road is adopted, it is the developer's responsibility.
What the paperwork shows
My FOI CN48965 brought back copies of ten separate Section 38 agreements for Middle Deepdale, signed between 2015 and 2026 by Keepmoat Homes, Kebbell Development and Linden. In every one, the bond is backed by the National House Building Council. Several had completion dates that passed years ago, the earliest being 31 December 2015.
What the council has told me
- The road agreements on the estate have been extended. Phase 3A runs to 1 February 2027, Phase D to 20 February 2027, and Phases E and F, along with the 2018 agreement covering Fox Way, Tawny Drive, Badger Lane and Pheasant Way, to 28 February 2027 (council email, 19 November 2026).
- The agreement of February 2023 covering Ancient Way, Discovery Lane, Maximus Way, Numeral Way, Roma Drive, Romulus Road and Shield Way has been extended to 28 April 2027 (FOI CN56223, 17 November 2026).
- The council says the main hold-up is that the sewers have not yet been put onto maintenance, which stops the roads being adopted. It has not had a formal request to inspect some of the roads, and the developers have not yet provided the electrical test certificates for the street lights (FOI CN56223 and council email, 19 November 2026).
- Until the roads are adopted, the developer is responsible for broken street lights and grit bins on the unadopted parts of the estate, and the council only grits adopted roads (council email, 19 November 2026).
- The bonds allow the council to complete the roads itself if a developer defaults (council email, 20 November 2026).
What I have asked and am waiting on
On 19 November 2026 I asked Yorkshire Water where the sewer adoption has got to, asked Keepmoat for dates for the sewers, street lighting and road adoption, and asked the council what it will do if the February 2027 dates are missed, including whether it would use the bonds. Earlier questions about the bonds, unfinished works and the streets with no agreement at all are still unanswered.
If a light is out, a grit bin is empty or the road surface is failing on Middle Deepdale, you can report it to me and I will chase the developer or the council. Email eastfield@damondewdney.co.uk if you would rather write directly.
See also my guides to reporting road problems and grit bins.
Useful links
- Road adoption, North Yorkshire Council [1]
- Section 38 guidance, December 2025 (PDF), North Yorkshire Council [2]
- Road records and the list of adopted streets. The council says only about five per cent of roads and streets in North Yorkshire have gone through formal adoption.